Made with Xara Web Designer
Dome construction begins with making a fabric form.
This can be done by one of two methods. The first
method is to sew together the polyester fabric and
attach it to the plywood base or concrete footing. The
fabric is then propped up and the urethane coating is
sprayed into it with the inflater fan running. When the
fabric becomes sufficiently sealed, the fabric form
inflates. The second method is to pre coat the material
before the gores are sewn together and seal the seams
after inflation with urethane coating.
We spray high density closed cell urethane foam on the
inside of the fabric form after it is completely sealed
with coating and cured out. We generally use 3#
density foam that has a compressive strength of over
50 psi. We apply the urethane foam in passes up to 3/4
inches thick until we reach the designated thickness
(usually 3 to 4 inches).
After spraying in the foam, we lay out the openings,
which is done in a variety of ways. In the downstairs of
our own home we have many openings where we
attached the rough frames to the dome shell (the foam
surface). We attached them plumb and filled in the
lacking areas with Styrofoam. We use the sprayed
polyurethane foam to then tie it all together and attach
it all the the foam insulated shell. Other large openings
we simply outlined with strips of extruded Styrofoam,
screwing them to the foam as a termination point until
the molded foam overhangs could be attached and the
re bar bent into them to tie them in structurally.
Re bar hangars are put into the foam in horizontal lines
according to engineering specs (usually 12 to 18 inches
between lines) from the floor to the very top. The
vertical re bar is attached to the horizontals so these
hangars are the only ones needed. We spray in the first
layer (1/2 to 3/4 inch) of concrete to hold in the re bar
hangars. In large openings we may put some re bar into
the first coat of concrete to help support the weight
load that will be sprayed above it. When the first coat
of concrete is sprayed all the way to the top and at
least a day old, we are ready to tie in the re bar.
Engineering provides for extra re bar around openings,
in the footing and any other special needs application.
With the re bar tied in place, we begin to shotcrete
with the footing. You’ll notice in the picture that the re
bar (vertical) comes down into the footing and is bent
horizontally. This allows us to spray in the footing and
move right up the dome shell without lap joints. This
also provides insulation against the footing without
having to spray it in from the outside later. You don’t
need any form boards for the footing as long as you’re
spraying at a slump of 2 1/2 inches or drier (the drier
the better). The rule of thumb is to spray the
shotcrete as dry as you can pump it. With a good S-
tube hydraulic concrete pump (the only kind I would
recommend) I have pumped down to 0 inches of slump
(I checked the slump when I was done spraying).
We spray in the re bar in 1 pass under normal
conditions and cross rake it when we are done to ensure
a uniform surface. This process is an important
preparation for the finish coat which will be troweled
while very plastic and sponge floated to leave a very
nice texture without any re bar lines. Some areas of
the dome shell require extra thickness of concrete
involving an extra pass or two. This includes around
doors, windows, and other openings. Ledges can also be
formed onto the shell inside to set 2nd story floor
joists on. Before we spray on the finish coat of
concrete, we attach window overhangs, dormers,
entryways etc. These units are urethane foam pieces
cast in molds that we design for single or multiple uses.
The final coat of concrete made of sand, cement and
additive must blend together the interior surface into
and attractive, textured finish. The interior of the
shell being finished, we move to the dome exterior. We
apply multiple coats of urethane rubber coating with
ceramic aggregate being blown into the first coat or
two for texture. This application provides a more
durable protection to the coated surface also.
Building Process
Click here to return to the top of the page
The building process covered herein is only for built in place thin shelled concrete domes. Our transportable, light
weight building process is similar. We will share pictures in the coming season.
Where Portable and Permanent Meet